This week’s update is pretty short.

The clean-up is done – for now.

Most of the bids for work are in and we are now waiting on the insurance company to give us the green light to start the roof repairs. Hopefully, it will be forth coming because we cannot do anything else until the roof is repaired.

Our working group met this morning with a local architectural firm to talk about the renovation and to get some professional input into the planning process. Next week we should have a better idea of the scope of the renovation and the cost over and above the insurance settlement.

Next week I will also put out a preliminary list of upgrades and changes that the working group is considering and solicit feedback from the parish.

Please note: the school Bathrooms are being renovated this summer. This means that the only bathroom in the building will be the faculty bathroom. The parish Hall bathrooms will be available for use during Mass. We apologize for the inconvenience, but this is the only time that MCPS can renovate.

No comments:

Post a Comment